Makati—(PHStocks)—South Luzon Thermal Energy Corp. (SLTEC) announces the start of operations of its second 135MW Unit (Unit 2) in Calaca, Batangas, doubling the capacity of the plant and bringing additional power supply to the Luzon grid. The 2 x 135MW coal power plant in Calaca, Batangas utilizes circulating fluidized bed technology (CFB) to reduce emissions and minimize adverse environmental impact.

SLTEC is the joint venture company of AC Energy Holdings Inc., a wholly owned subsidiary of Ayala Corp. (PSE: AC), and Trans-Asia Oil and Energy Development Corp. (PSE: TA).

Construction of Unit 2 was completed in the second half of 2015. It was synchronized to the grid on August 15, 2015 and passed reliability and performance tests early this year.

Unit 1 started commercial operations on April 24, 2015 and achieved gross generation output of 553.8 GWh by the end of 2015. The unit is currently under annual preventive maintenance.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.